Library Second Floor
Project Dates: May 16-Aug 12
Project Coordinator: Rob Luke
University Hall Room 108
Project Dates: May 14-July 31
Project Coordinator: Robert Hanlon
Water Line Project
Phase I: April 18-May 12
Phase II: May 13-May 31
Phase III: June 1-June 16
Project Coordinator: Jeff Johnson
TD Industries (Energy Conservation Project)
January-June 3
Project Coordinator: Larry Harrison
Notes by Symbol:
1. Library Dumpster Locations
June 6-July 20
2. Motorcycle Parking Blocked From:
May 16-June3
July 21-August12
3. Library Contractor Staging Area:
May 16-August 12
4. University Hall Dumpster Location:
May 14-July 31
5. University Hall Contractor Staging Area:
May14-July 31
6. University Hall Intermittent Work Area:
Used as Needed
7. Fenced in Area for VAV Boxes