Week of January 24, 2011

ERB Parking Lot 34

Starting on Monday February 7th repair work will begin at parking lot 34 at the corner of UTA Blvd and Nedderman. The field offices currently located there will begin to dismantle. We will also be seal coating and striping the parking lot. From Feb. 17th – 20th drivers will need to use the south entrance/exit to avoid the work.   Pending weather conditions the parking lot will be available for UTA use on Monday Feb. 21st.

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Early Morning Concrete Pour

We have scheduled an early morning pour of the Upper Level Slab #6 at the College Park Center site for Thursday, January 27, 2011 at 2am. We will begin setting up the pump equipment at 2am with the concrete arriving to the site beginning at 2 am.  This 250 cy pour should be completed prior to 8 am. This pour is being made at night to minimize effects of the construction traffic mixing with the University traffic.