College Park Center Project Site
An early morning concrete pour at the CPC project site has been scheduled for Tuesday, November 2, 2010 at 2:00 am at the main concourse #1. Equipment will begin arriving between 12:30am & 1:00 am to setup. The pour should be completed prior to 7:00am on Wednesday. The concrete pour is being made early to help prevent the numerous concrete trucks from interfering with University traffic on Wednesday.