Week of July 12th, 2010

UTA Blvd Closure

UTA Blvd is closed to allow the new lighted crossway to be installed. The street will remain closed until the new pavers and lighting system is installed, approximately 2-3 weeks. Barricades and signage have been installed.

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Pecan Street Status

Ark contracting is completing the street patching on 3rd Street, and is cleaning up the site. They will start the water line installation for College Park this week. After the water line installation the Arlington Hall parking lot surface will be restored for use in August.

Sidewalk repairs at 2nd & Pecan have been completed.

The Bookstore Parking Lot is back in operation.

UTA Electric shop is working on the new lighting installations for Pecan Street.