Week of March 22, 2010

Parking Lots 45 & 49 Update

The changes in Parking Lots 45 & 49 have been completed and are ready for returning students.

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Parking Lots 51 & 56 Update

These two lots are not scheduled for completion until March 31st, but the pavement and curb work is completed. The lots still need striping and general cleanup.

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Speer Street Update

Speer street was completed late Friday night. This area still needs some cleanup but the street is open for traffic as of this morning.

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

City of Arlington Update

The city contractor completed the storm line and sidewalk Friday. They will be finishing up the punch list this week and closing out the project.

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Pecan Street Overhead Lines/ Storm Line Installation Update

The new storm line is in place from the park area up the corner of Pecan and 3rd Street. The communications duck bank is completed from 4th Street to about half the next blockĀ  allowing the contractor to get off the Lipscomb site. Final cleanup should be done today.