Week of March 17th, 2010

Pecan Street Overhead Lines/ Storm Line Installation Update

The contractor is working on the installation of the 4 x 6 drainage line on the north side of Lipscomb Hall.

Construction Timeline:

Work should be completed along the north of Lipscomb by March 22nd

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Speer Street Update

The contractor has completed the curb installation and is working on the final grade and base installation.

Construction Timeline:

Asphalting is scheduled to start Thursday to allow the street to be completed and ready for use by Monday, March 22nd

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

City of Arlington Update

The line is installed across Mitchell Street and the contractor is in the process of framing for the new sidewalks and doing the final patch across Mitchell Street.

Construction Timeline:

The goal is to have the entire intersection open no later than Monday, March 22nd for returning students.

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Parking Lot 49 / Doug Russell Street Changes Updates

The city has completed the installation on the “no parking signage” along Doug Russell to help with the traffic flow.  The seal coating of  lot 49 is underway.  As soon as the seal coating is completed the re-striping of the lot and the turn arrows on Doug Russell will be completed.

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Parking Lot 45 Update

The concrete work is scheduled today along with some additional patch work in the lot.  We will be re-striping  this lot in order to increased parking
and eliminate the need for any overflow parking into lot 53 next fall saving commuter spaces.

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Parking Lot 51 and 56

New Lot 56 on Pecan Street at Johnson Crossing will add 116 spaces.

Lot 51 will be expanded to add 79 spaces.

Construction Timeline:

These two lots are moving along as scheduled. They should be finished some time toward the end of March as scheduled.

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Parking Lot 50

Lot 50 has been expanded to add 50 additional spaces.The expansion is complete, with some minor landscaping to still be completed.